Hang Lung project in Zhongjie Street has been closed according to schedule and begins acceptance of divisional work (photoes and news ).
Hang Lung Imperial Square project in Zhongjie street that supervised by our company is an important project of Shenyang City. It is the first time strategic cooperation between our company and the third largest listed real estate company of Hong Kong--Hang lung real estate company. Recently the project has been fully closed. This ensured the execution of winter construction. The acceptance of divisional work has been carried out continually. If everything goes properly, the Square will open in June, 2010. The closing of the project ensured the realization of the controlled progress of Hang Lung project in Zhongjie Street.
	Since the establishment of the supervision 
department of Hang Lung project in Zhongjie street, under the leadership
 of supervisor Liu Yong, Yang Zhaoshun, the supervision team are 
responsible with their work. From the night stand in concrete pouring to
 the control of winter construction quality and safety, our supervision 
engineers have been praised by participating companies and consultants 
group. Now the project has the conditions for acceptance of divisional 
work. This is the basis for the opening of Hang Lung Imperial Square in 
June,2010.
 
  
Roof 1, tree-branch steel columns, girders and rooflighting sheet have been installed.
	
 Rolling stair is operating in installation and adjusting process.
 
	 
Indoor toilet room decoration
	 
Fireproofing work of tree-branch steel columns and girders has been completed.
	
 Curtain wall in the side of Zhongjie street 
	
 Curtain wall in the east side