	China aid project Cote d'Ivoire Gagnoa hospital has successfully passed the mid-term acceptance. 
 
January
 9, 2010,  mid-term acceptance team, 6 people came to inspect China aid 
project Cote d'Ivoire Gagnoa hospital. The quality inspection and 
acceptance lasted one week.  
 
The inspection team was formed by 6
 people: Official Wu Jie, from Department of Foreign Aid of Ministry of 
Commerce; official Wang Yue, from Department of Cooperation; team leader
 Huang, engineer Zheng, engineer Fu and engineer Hao from Chinese Civil 
Engineering Group Co., Ltd.. After the Inspection team arrived at the 
site, they held first meeting of mid-term acceptance, seminars with 
supervisors, representatives of designers and technology team. Economic 
Consultation Department Secretary Dong Shengli participated in the last 
meeting of the mid-term acceptance. 
	During the inspection, they mainly inspected the paper documents and they measured the quality of construction body at site.
       
In
 the inspection of the documents and files: they made sampling 
inspection about the process and quality control documents, acceptance 
records of concealed works, change of design that formed during the 
construction process. They consulted the construction organization 
design, technology requirements, construction diaries, training records 
and records of safety managements. 
	In
 the inspection of the quality of construction entities: mid-term 
acceptance team made sampling inspection about the entities. The 
sampling sites were Building A (Clinic Building A), Building B (Clinic 
Building B), Building C (emergency clinic and administration building), 
Building D (medical technology building and operating department),  
Building E (Obstetrics and Gynecology Ward Building),  Building F 
(pediatric ward Building),  Building G (Surgical Ward Building),  
Building H (medical ward Building). The sampling items were: concrete 
columns, beams, masonry wall verticality, wall roughness, and the 
measurements of the holes of doors and windows, the measurements of the 
construction axes. The sampling items, 100% were qualified.
 
The 
assessment of mid-term acceptance team: Building A (Clinic Building A), 
Building B (Clinic Building B), Building C (emergency clinic and 
administration building), Building D (medical technology building and 
operating department),  Building E (Obstetrics and Gynecology Ward 
Building),  Building F (pediatric ward Building),  Building G (Surgical 
Ward Building),  Building H (medical ward Building). The foundation and 
it's branches work and the main structural branches of the above were 
qualified. The foundation and it's branches work of Building N 
(equipment room 2), Building Q (Water Tower) were qualified. 
	Through
 one week inspection, the mid-term quality inspection and acceptance 
team were satisfied with the work of the supervision team. They knew our
 supervision team had played the supervision function for construction 
quality and management. They thanked our supervision team for their 
cooperation and support in the inspection process. They mentioned the 
progress of the project. For the schedule has been delayed, official 
Wang Yue, from Department of Cooperation asked the technology team to 
increase the speed the construction so that the project can be handed 
over to Cote d'Ivoire.
 
January 15, 2010, the China aid project 
Cote d'Ivoire Gagnoa hospital successfully passed the mid-term 
acceptance. Our supervision team were confident that in the follow-up 
work, they could make persistent efforts. Under the leadership of the 
Economic Consultation Department, our supervision team would cooperate 
with the design company representatives and construction company, they 
would control the quality and increase the speed and would ensure the 
transfer of the project in time. 
	
 
 
The first meeting of the mid-term acceptance
 
 
Inspection team on-site inspection ( right 3, our company supervision team leader Mu Zhenxing)
	 
	supervision team leader Mu Zhenxing (left 1) accompanied the  inspection team on-site inspection
	 
 
Inspection team on-site inspection (left 2, our equipment supervision engineer Fu Dongsheng )